Plan
of implementation |
Technical Information |
P
lan of implementation
Presentation
of idea
February 7, 1997
RelationShip becomes a project of the
University of Applied Sciences FH
Furtwangen
April 2, 1997
Public presentation
April 23, 1997
Completion of the 1:10 model
June 1997
Installation
of hull and rigging
November 1997
Transport
via helicopter to the Rhine
January 1998
Presentation at the boot Düsseldorf
17.-25. January 1998
Test cruise with crew to Lissabon
June / Julyl 1998
Plan of the voyage
Bayona - La Palma 29 June 1999 (1000 Mm)
La Palma - Dakar July 1999 (900 Mm)
Dakar - Receife August 1999 (1700 Mm)
Receife - Trinidad October 1999 (1800 Mm)
Trinidad - Bermudas December 1999 (1300 Mm)
Bermuda - New York February 2000 (700 Mm)
New York - Irland April 2000 (2900 Mm)
Irland - Wilhelmshaven April 2000 (900 Mm)